Despite the COVID-19 challenges, the construction project remains on schedule. In fact, now that Governor DeWine has closed schools until May 1st, we have instructed the construction team to start working on a portion of their summer work in hopes that we can get ahead in case there are future delays due to material or human resource shortages. Already this week, the construction team has started demolition in the courtyard area. In the next few weeks, we will be pouring the concrete slab and finishing the roof deck in the South Wing and then moving to the North Wing to complete the same process.